Ex-head of Boryspil district administration's firm got UAH 2 bn in uncontested orders

The company RSE Group Ukraine, controlled by Andrii Hrynenko, former head of the Boryspil District State Administration, received 7 state orders worth UAH 2.08 bn in 2026. Six of them were signed without tenders, and in the seventh, for generating units for the Kyiv Aviation Institute, the firm was the only bidder.
The Kyiv Aviation Institute bought two Czech cogeneration units for UAH 143,137,200 (about $3.3 mn) from the firm of Andrii Hrynenko, former head of the Boryspil District State Administration, and no competitors turned up in this tender, Nevероятно, но факт… reports. For the company RSE Group Ukraine it is already the seventh state order of 2026. Together they are worth UAH 2.08 bn (about $47 mn). Customers signed six contracts with it directly, without tenders. In the seventh, the university one, the firm competed against itself.
A tender for five units in order to buy two
The institute announced tender UA-2026-10-26-007001-a on 26 October. A bidder had to prove that in 2024-2026 it had already supplied five units with a capacity of 2,300 kW or more. Curiously, the university itself was buying only two. In other words, the customer set the experience bar 2.5 times higher than its own need, and such a requirement weeds out smaller suppliers.
After a complaint, the institute softened the requirement. Experience of supplying two units was now enough, and the period over which it was counted was extended back to 24 February 2022. However, the contracts by which a bidder confirmed its experience still had to be fully performed. On 5 November the documentation was amended once more, and the customer rejected a request to extend the deadlines because the money for the purchase is available only in the 2026 budget.
On 18 November the only bidder, RSE Group Ukraine, was declared the winner, and on 26 November the parties signed the contract. There were no savings at all. The firm offered UAH 119,281,000 without VAT, and the contract was signed for the same amount with VAT, that is, for UAH 143,137,200. Each RSE 2300 unit costs UAH 71,568,600, and the firm must deliver them by 20 December.
For this money the university will receive units with a capacity of 2.3 MW and a voltage of 10.5 kV, with an MWM TCG 3020 V20 R engine and a VWKG 2300H boiler. The package includes cooling, ventilation, gas supply, automation and fire protection systems. The unit's electrical efficiency is 44%, thermal 43%, total 87%. The warranty is valid for 2 years after start-up or 2.5 years after delivery.
Where the firm came from
RSE Group Ukraine (code 44971187) is by no means a new company. It was registered on 18 November 2022 under the name Axis Technology and belonged to Oleksandr Chyzh. Everything changed within a week in November 2025. On 19 November the company was renamed, on the 21st Anna Pozdniakova became director, on the 26th the Czech RSE s.r.o. became the owner, and on the 27th Andrii Hrynenko was recorded as the ultimate beneficiary. On 6 March 2026 the firm's charter capital grew from UAH 10,000 to UAH 7,853,217.
The firm is registered in Kyiv at 40 Ushynskoho Street, premises 302, office 1. Another 53 companies are registered at the same address. Valerii Ivanov is listed as the firm's representative. Since 23 January 2026 RSE Group Ukraine has also owned the company PowerTech Service (code 45226059).
The firm's history is best shown by its financial statements. For 2025 it did not earn a single hryvnia, had a loss of UAH 2.178 mn, assets of UAH 5.653 mn, liabilities of UAH 7.841 mn and two employees. For the first half of 2026 revenue was already UAH 1.328 bn, profit UAH 3.423 mn, assets UAH 25.992 mn, liabilities UAH 4.177 mn, and 12 people worked at the firm. So the company got its billion in revenue practically from zero, and the February contracts with a state enterprise alone, discussed below, exceeded UAH 1.58 bn.
A billion without tenders
The firm's biggest client became the state enterprise Restoration of Critical Infrastructure (code 38054466), which is subordinate to the Restoration Agency. On 9 February 2026 the enterprise signed four contracts with RSE Group Ukraine without tenders for UAH 1,584,332,966.40, that is, about $36 mn (1, 2, 3, 4). The purchases were approved as early as 30 January as urgent wartime needs.
Under these contracts the state enterprise bought equipment for municipal energy and pumping stations: - six RSE 2300 units at UAH 72.54 mn each; - three RSE 4500 units at UAH 121.72 mn each; - ten diesel units at UAH 52.67 mn each; - five mobile generators at UAH 52.25 mn each.
On 29 September Kyivteploenergo ordered four diesel units directly from the firm for UAH 210,779,736. On 26 October the state enterprise Restoration of Critical Infrastructure signed another direct contract with it for UAH 143,250,206.40. Together with the university this makes UAH 2,081,500,108.80.
Of this sum the firm received UAH 1,938,362,908.80 without tenders, that is, 93.1%. It has only three customers, and one state enterprise gave UAH 1.728 bn, that is, most of all the orders.
Manufacturer and supplier in the same hands
The Czech company RSE s.r.o. (code 19213913) was registered in Brno on 3 April 2023 and is 100% owned by Hrynenko. Since January 2025 it has itself received Ukrainian state orders worth UAH 888.71 mn. For example, in May 2026 the Dnipro municipal enterprise Komenerhoservis bought four RSE 2300 units directly from it for €5.08 mn, or UAH 260.40 mn without VAT. This money is not included in the Ukrainian firm's UAH 2.08 bn, so the orders named alone for both companies in 2026 exceed UAH 2.34 bn.
So Hrynenko controls both the Czech manufacturer and the Ukrainian firm that sells its units to the state. What this means for the budget is shown by the price per megawatt of capacity. The university paid €624,000 per MW without VAT. Dnipro bought the very same RSE 2300 units from the same group at €552,000 per MW without VAT, so the university paid roughly 13% more. The Polish analogues bought by the Restoration Agency cost €583,000 per MW with VAT. The German Rolls-Royce MTU unit for the Cherkasy CHP plant cost €635,000 per MW with VAT. The February RSE units for the state enterprise cost $731,000 per MW with VAT.
These figures should be compared directly with caution, because the units' configurations differ. Independent journalists assessed the February prices as market ones. However, the university purchase looks more expensive than the Dnipro one from the same manufacturer, even though a tender should have lowered the price. There was no competition in it, so there was no one to lower the price.
Who Andrii Hrynenko is
Hrynenko headed the Boryspil District State Administration in 2013-2014, under the presidency of Viktor Yanukovych. Before that he worked in district administrations and banks. In 2014 Hrynenko ran for office from the Strong Ukraine party. In 2015 he became a co-founder of the Clear Energy group, which works with biogas and biomass and builds power plants.
No authority has so far established any violations of the law in these purchases. Direct wartime contracts are permitted, and journalists found the February prices to be market ones. Still, the picture is telling. A firm that had no income at all in 2025 received over UAH 2 bn of public money in 2026, and almost all of it came to it without competition. In the one tender where competitors could theoretically have appeared, the customer began with an experience requirement 2.5 times greater than the purchase itself, and ended with one bidder.
Source:Невероятно, но факт…
References:t.meopendatabot.uaopendatabot.uaopendatabot.uaprozorro.gov.uaprozorro.gov.uaprozorro.gov.uaprozorro.gov.uaprozorro.gov.uaprozorro.gov.uaprozorro.gov.uaclarity-project.infonashigroshi.orgnashigroshi.org